T2-6 New Bridge: SPM T Jacking Transport Bridge Section of Beam Storage Yard
T2-6 New Bridge: SPMT precise positioning, fine-tuning placement
T2-6 New Bridge: SPMT precise positioning, fine-tuning placement
T2-6 New Bridge: Positioning completed, SPMT pack carrier returned to the beam storage yard
In this task of demolishing and building the flyover, the new beam of the No. 5 flyover is the heaviest, 40 meters long, 12 meters wide, and weighs more than 700 tons, which is equivalent to the weight of more than 500 ordinary cars. "Since the weight of the beam body carried is about 500-700 tons, the balance of the beam body should always be maintained during transportation to avoid overturning. The four groups of modular vehicles must be synchronized when carrying the beam body, and the driving speed of the modular vehicles must be accurately controlled, which is about 8 meters per minute.
T2-5 New Bridge: SPMT jacking, transportation
T2-5 New Bridge: SPMT precise positioning, fine-tuning placement
T2-5 New Bridge: Positioning is completed, and the SPMT pack carrier is returned to the beam storage yard
It is reported that since the use of SPMT module intelligent transfer technology in the Kaiyang Expressway Reconstruction and Expansion Project, this is the first time that the same demolition and construction of the overpass has been implemented nationwide, and the demolition of 2 old bridges and the erection of 2 new bridges have been realized within 3 hours.